PointReleaseProcess

Differences between revisions 1 and 26 (spanning 25 versions)
Revision 1 as of 2007-12-13 15:17:02
Size: 2187
Editor: 82-69-40-219
Comment: initial incomplete draft
Revision 26 as of 2010-07-08 16:40:35
Size: 4322
Editor: 82-69-40-219
Comment: update various things for lucid
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
''This is an incomplete DRAFT.''

To be carried out by: nominated stable release manager, with support from the [https://launchpad.net/~ubuntu-sru stable release updates] and [https://launchpad.net/~ubuntu-release release teams]
To be carried out by: nominated stable release manager, with support from the [[https://launchpad.net/~ubuntu-sru|stable release updates]] and [[https://launchpad.net/~ubuntu-release|release]] teams
Line 10: Line 8:
Planning stages, for LTS point releases:
 1. Discuss candidates for new or improved hardware support with affected parties, including the Canonical support team (via Steve George) and the Ubuntu kernel team.
 1. Establish a hit-list of bugs to fix in the point release.
Between Release minus 6 months and Release minus 2 months:
 1. Discuss candidates for new or improved hardware support with affected parties. Some sources for this work should be:
  *
the Canonical support team (via Steve George)
  * customers
  *
the Ubuntu kernel team
  * the Ubuntu QA team

 1. Establish a hit-list of bugs to fix in the point release using a milestone.  Milestoning bugs is not a commitment to including the changes in the point release; they may be deferred after further information becomes available.
Line 14: Line 16:

Release minus 2 months:
 1. Process stable release updates [[StableReleaseUpdates|as normal]]. For hardware-enabling fixes, the package should be tested on the affected hardware prior to submitting to sign-off for -proposed.
Line 17: Line 22:
Process stable release updates [:StableReleaseUpdates:as normal]. Once an acceptable number of bugs is believed to be fixed, start building test CD images:
 1. If the kernel or associated modules has been changed, upload `debian-installer` after all the binaries are in place. If the ABI changed, make sure to take account of this throughout `debian-installer/build/config/` and in the `installer` seed for all flavours being built.
Release minus 1 month:

 1. In coordination with QA, verify that all candidate bugs are fixed.
 1. Upload a new `base-files` package to -proposed to bump the `lsb_release` description ([[http://changelogs.ubuntu.com/changelogs/pool/main/b/base-files/base-files_4.0.1ubuntu5.8.04.8/changelog|example for 8.04.4]]). Do not change the DISTRIB_RELEASE value, which is used programmatically by third-party software.
 1. If the kernel or associated modules have been changed, upload `debian-installer` after all the binaries are in place. If the ABI changed, make sure to take account of this throughout `debian-installer/build/config/` and in the `installer` seed for all flavours being built.
 1. Notify Evan Dandrea to update umenu and wubi for the point release.
Line 20: Line 29:
 1. Change `cdimage/bin/run-germinate` and `debian-cd/CONF.sh` to build from -proposed temporarily. If live CDs need to be built, also modify `cdimage/bin/buildlive`.
 1. Build CD
images (which will be published and smoke-test in some convenient environment to check for obvious failures.
 1. Contact IS, QA, and/or certification as appropriate to request testing.
 1. Once testing is verified to be complete, release images as final, and move the previous images to `old-releases.ubuntu.com`. TODO much more detail here
 1. Change `cdimage/bin/run-germinate` and `debian-cd/CONF.sh` to build from -proposed temporarily.
 1. Build
CD images (which will be published on cdimage.ubuntu.com) and smoke-test in some convenient environment to check for obvious failures.
Line 25: Line 32:
TODO:
 * actual release process
 * `lsb_release` et al?
 * Anything else?
Release minus 3 weeks:
 1. Contact IS, QA, and/or certification as appropriate to request testing for hardware recertification.
 1. Iterate CD images as needed based on testing feedback, in coordination with the kernel team.

Release minus 6 days:
 1. Once testing is verified to be complete, move packages to -updates.
 1. Prepare change summary and release announcement
  * script to use for preparing the change summary: http://people.canonical.com/~cjwatson/lucid-updates.py
  * if this is the final point release for the distroseries (because a new LTS will be released soon), include a reminder of this and of the support cycle/EOL.
 1. Notify Matthew Nuzum of the upcoming point release.

Release:
 release images as final, and move the previous images to `old-releases.ubuntu.com`:
  * Check with James Troup whether the previous point release needs to be moved off before prepublishing due to mirror space constraints.
  * Prepublish images:
  
  {{{DIST=lucid for-project ubuntu publish-release ubuntu-server/daily 20100708 server poolonly}}}

  (similar for alternates, desktops, etc.)

  * TODO much more detail here
  * Notify Matthew Nuzum to update the iso URLs on the ubuntu.com website

 1. Create a snapshot of the archive:

 {{{lp_archive@cocoplum:~$ point-release-snapshot lucid lucid.1-security-updates-snapshot}}}

 which will create a hardlink farm in `~lp_archive/point-releases/`.

 1. File a bug on [[https://bugs.launchpad.net/ubuntu-website/+bugs|ubuntu-website]] to have https://help.ubuntu.com/community/UbuntuHashes updated.

 1. send the announcement mail

Release +1 day:

 1. restore the .manifest.full file on releases.ubuntu.com

To be carried out by: nominated stable release manager, with support from the stable release updates and release teams

Goals:

  • Refresh hardware support in LTS releases for carefully-selected hardware
  • Roll up accumulated stable updates into updated images to reduce download requirements for new deployments
  • Maintain stability of existing installations

Between Release minus 6 months and Release minus 2 months:

  1. Discuss candidates for new or improved hardware support with affected parties. Some sources for this work should be:
    • the Canonical support team (via Steve George)
    • customers
    • the Ubuntu kernel team
    • the Ubuntu QA team
  2. Establish a hit-list of bugs to fix in the point release using a milestone. Milestoning bugs is not a commitment to including the changes in the point release; they may be deferred after further information becomes available.
  3. In concert with affected developers, triage the hit-list for feasibility.

Release minus 2 months:

  1. Process stable release updates as normal. For hardware-enabling fixes, the package should be tested on the affected hardware prior to submitting to sign-off for -proposed.

  2. Discuss the possibility of a Canonical press release for the point release with Gerry Carr.
  3. Liaise with IS, QA, and certification to arrange for testing resources.

Release minus 1 month:

  1. In coordination with QA, verify that all candidate bugs are fixed.
  2. Upload a new base-files package to -proposed to bump the lsb_release description (example for 8.04.4). Do not change the DISTRIB_RELEASE value, which is used programmatically by third-party software.

  3. If the kernel or associated modules have been changed, upload debian-installer after all the binaries are in place. If the ABI changed, make sure to take account of this throughout debian-installer/build/config/ and in the installer seed for all flavours being built.

  4. Notify Evan Dandrea to update umenu and wubi for the point release.
  5. Change cdimage/bin/make-web-indices, cdimage/bin/publish-release, and debian-cd/CONF.sh to use the new release version number.

  6. Change cdimage/bin/run-germinate and debian-cd/CONF.sh to build from -proposed temporarily.

  7. Build CD images (which will be published on cdimage.ubuntu.com) and smoke-test in some convenient environment to check for obvious failures.

Release minus 3 weeks:

  1. Contact IS, QA, and/or certification as appropriate to request testing for hardware recertification.
  2. Iterate CD images as needed based on testing feedback, in coordination with the kernel team.

Release minus 6 days:

  1. Once testing is verified to be complete, move packages to -updates.
  2. Prepare change summary and release announcement
  3. Notify Matthew Nuzum of the upcoming point release.

Release:

  • release images as final, and move the previous images to old-releases.ubuntu.com:

    • Check with James Troup whether the previous point release needs to be moved off before prepublishing due to mirror space constraints.
    • Prepublish images:

      DIST=lucid for-project ubuntu publish-release ubuntu-server/daily 20100708 server poolonly (similar for alternates, desktops, etc.)

    • TODO much more detail here
    • Notify Matthew Nuzum to update the iso URLs on the ubuntu.com website
  • Create a snapshot of the archive:

    lp_archive@cocoplum:~$ point-release-snapshot lucid lucid.1-security-updates-snapshot

    which will create a hardlink farm in ~lp_archive/point-releases/.

  • File a bug on ubuntu-website to have https://help.ubuntu.com/community/UbuntuHashes updated.

  • send the announcement mail

Release +1 day:

  1. restore the .manifest.full file on releases.ubuntu.com

PointReleaseProcess (last edited 2022-02-22 09:39:35 by sil2100)