MaverickReleaseStatus

Differences between revisions 2 and 15 (spanning 13 versions)
Revision 2 as of 2010-06-18 15:18:07
Size: 2229
Editor: 81-65-197-161
Comment:
Revision 15 as of 2010-08-20 15:25:12
Size: 1999
Editor: 81-65-190-198
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
 * [[http://people.canonical.com/~pitti/workitems/maverick/canonical-dx-team-ubuntu-10.10-beta.html|10.10 beta burn-down chart]]
Line 3: Line 4:
[[http://people.canonical.com/~pitti/workitems/maverick/canonical-dx-team-maverick-alpha-2.html|Alpha-2 burn-down chart]]

Milestoned Features for alpha-2:
Milestoned Features for ubuntu-10.10-beta:
Line 7: Line 6:
  * new release with transient menus support and a nasty lock issue fixed; more apps supported: please keep on testing the new versions
  * see https://wiki.ubuntu.com/DesktopExperienceTeam/ApplicationMenu for how you can help
  * tight, but on track for A2
   * Status: 95% finished, missing a nautilus patch; bug fixes targeted post aug.26th to address some remaining perf. issues and dealing with unresponsive applications
Line 12: Line 9:
  * csd not in scope for maverick anymore (more on that later); basically we're reconsidering the integration issues with the rest of the community
  * argb has been taken out as well; we plan to re-introduce it after a2, once more bug fixes can be confirmed; still in scope for Maverick
  * will update the BP work-items to reflect that
   * Status: 100% finished, but by postponing argb (can be an issue)
Line 17: Line 12:
  * new release with registration + a new set of controls in the menu
  * RB & Amarok enabled to support the new menu features
  * on track for A2
   * Status: 90% finished, stuck on last minute mprisv2 changes; Monday deadline agreed with the desktop team

 * [[https://blueprints.edge.launchpad.net/ubuntu/+spec/dx-m-indicator-clock|dx-m-indicator-clock]]
   * Status: 90% finished, upgrade script to be ironed out with didrocks next week
Line 22: Line 18:
  * will be re-targeted for A3   * Status: 30% finished, scoped down features up to UIF

Critical/High Milestoned Bugs, ie "bugs on our radar":
 * See https://bugs.launchpad.net/ayatana/+milestone/ubuntu-10.10-beta
Line 25: Line 24:

Critical/High Milestoned Bugs, ie "bugs on our radar":
 * See https://bugs.launchpad.net/ayatana/+milestone/ubuntu-10.04-alpha-2, in particular:
  * LP:# -
Line 33: Line 28:
  * New weekly release (a bit of lag due to a lot of new packages)
  * On track for A2
  * Lucid PPA also available at: http://launchpad.net/~canonical-dx-team/+archive/une
  * Status: 90% finished, on track for the release
Line 38: Line 31:
  * Minor changes released this week
  * Still more backend bugfixes
  * *Not* on track for A2 for the UI part - we'll continue releasing engineering prototype interfaces to exercise the backend
  * Status: Not feature complete, will not be proposed as a UNE default; develop continues nonetheless; good progresses
  * Will stay in universe, along with its dependencies

Critical/High Milestoned Bugs, ie "bugs on our radar":
 * See https://bugs.launchpad.net/unity/+milestone/2010-08-26

Desktop

Milestoned Features for ubuntu-10.10-beta:

  • dx-m-app-menubar

    • Status: 95% finished, missing a nautilus patch; bug fixes targeted post aug.26th to address some remaining perf. issues and dealing with unresponsive applications
  • dx-m-gtk-enhancements

    • Status: 100% finished, but by postponing argb (can be an issue)
  • dx-m-sound-menu-v2

    • Status: 90% finished, stuck on last minute mprisv2 changes; Monday deadline agreed with the desktop team
  • dx-m-indicator-clock

    • Status: 90% finished, upgrade script to be ironed out with didrocks next week
  • dx-m-indicator-me

    • Status: 30% finished, scoped down features up to UIF

Critical/High Milestoned Bugs, ie "bugs on our radar":

Netbook

  • dx-m-unity-une-integration

    • Status: 90% finished, on track for the release
  • dx-m-indicator-network

    • Status: Not feature complete, will not be proposed as a UNE default; develop continues nonetheless; good progresses
    • Will stay in universe, along with its dependencies

Critical/High Milestoned Bugs, ie "bugs on our radar":

DesktopExperienceTeam/MaverickReleaseStatus (last edited 2010-10-01 15:28:16 by 81-65-196-239)